Tracker

CT Plan Progress Tracker

Current period Q3 2026

Nov 2024 – Apr 2027

Set up CT Plan Governance

(Dependent on SEC approval of CT Plan)

# Task Planned or actual Start End Months Completed % Done
1.1 Designation of Member Representatives Plan Nov 2024 Nov 2024 1 — 100%
Actual Nov 2024 Nov 2024 1 30 Nov 2024
1.2 Determine interim funding (to pay for counsel, RFP advisory firm, Administrator, etc.) Plan Nov 2024 Dec 2024 2 — 100%
Actual Nov 2024 May 2025 7 15 May 2025
1.3 Hire Outside Counsel Plan Dec 2024 Dec 2024 1 — 100%
Actual Dec 2024 Dec 2024 1 15 Dec 2025
1.4 Hire Communications Firm Plan May 2025 May 2025 1 — 100%
Actual May 2025 Jun 2025 2 25 Jun 2025
1.5 Advisory Committee Formation - announcement, interviews, OpCo vote Plan Dec 2024 Feb 2025 3 — 100%
Actual Dec 2024 Feb 2025 3 19 Feb 2025
1.6 Engage Processor(s) - contracts, SLAs Plan Feb 2025 Jul 2025 6 — 90%
Actual Feb 2025 — — —
1.7 Hire accounting firm to manage expenses Plan — — — — 100%
Actual May 2025 Jun 2025 2 23 Jun 2025
1.8 Launch Website (thectplanllc.com) Plan — — — — 100%
Actual Jul 2025 Aug 2025 2 29 Aug 2025

New Fees, Policies, and Data Subscriber Agreements

(Dependent on Advisory Committee formation - To be prepared in parallel with Workflow process to select new Administrator)

# Task Planned or actual Start End Months Completed % Done
2.1 OpCo and Advisory Committees to determine new fees/policies Plan Feb 2025 Sep 2025 8 — 100%
Actual Feb 2025 Oct 2025 9 —
2.2 Draft fee filing (and any related policies that need to be filed) Plan Oct 2025 Oct 2025 1 — 100%
Actual Nov 2025 Dec 2025 2 11 Dec 2025
2.3 File and Obtain approval of fee filing Plan Nov 2025 Aug 2026 10 — 100%
Actual Nov 2025 Jun 2026 8 —
2.4 OpCo and Advisory Committees to determine policies (to the extent separate from fee filing, e.g., direct v indirect bill) Plan Feb 2025 Oct 2025 9 — 75%
Actual Feb 2025 Aug 2026 19 —
2.5 OpCo to work with counsel to develop new data subscriber agreements Plan Nov 2025 Mar 2026 5 — 70%
Actual Feb 2026 Aug 2026 7 —

Selection of New Administrator

(Dependent on Advisory Committee Formation and Interim Funding)

# Task Planned or actual Start End Months Completed % Done
3.1 Hire Advisory Firm To Manage RFI/RFP Process - announcement, interviews, decision Plan Feb 2025 Feb 2025 1 — 100%
Actual Feb 2025 Jun 2025 5 30 Jun 2025
3.2 Draft RFP for New Administrator Plan Mar 2025 May 2025 3 — 100%
Actual Jul 2025 Sep 2025 3 26 Sep 2025
3.3 Advertise & Solicite Response to RFP Plan May 2025 Jun 2025 2 — 100%
Actual Sep 2025 Nov 2025 3 14 Nov 2025
3.4 Advisory firm evaluates bids and provides preliminary recommendations (e.g., narrowing of bids) Plan Jul 2025 Jul 2025 1 — 100%
Actual Nov 2025 Nov 2025 1 —
3.5 Operating Committee conducts Interviews ( potential for revised bids, subject to quality of RFP responses) Plan Aug 2025 Nov 2025 4 — 100%
Actual Dec 2025 Dec 2025 1 2 Dec 2025
3.6 Operating Committee votes on New Administrator Plan Dec 2025 Dec 2025 1 — 100%
Actual Dec 2025 Dec 2025 1 17 Dec 2025

Contract Negotiations with New Administrator

(Potentially dependent on fees and policies being finalized, which could impact scope of services)

# Task Planned or actual Start End Months Completed % Done
4.1 Operating Committee negotiates Administrative Services Agreement and SLAs with New Administrator Plan Jan 2026 Apr 2026 4 — 100%
Actual Feb 2026 May 2026 4 —

Administrator Setup

(Dependent on fees, policies, and data subscriber agreements being finalized and contract/SLA with new Administrator executed)

# Task Planned or actual Start End Months Completed % Done
5.1 Develop systems that tailor to Plan requirements to support account information, track vendor relationships, billing, interactive licensing tool. Allow for customers to: • View account profile, subscriptions, entities they are redistributing • View invoices • Report usage and external redistribution • Submit contracts online • Submit data feed requests *Dependent on Firm Setup* Plan May 2026 Jul 2026 3 — —
Actual May 2026 — — —
5.2 Hire Staff to support all functions (e.g., customer services/account management, customer audits, Plan services, accounting) Plan May 2026 Jul 2026 3 — —
Actual May 2026 — — —
5.3 Transfer existing customer data from UTP and CTA plans to new Administrator Plan Jun 2026 Oct 2026 5 — —
Actual Jul 2025 — — —
5.4 Standup New Plan Website Plan May 2026 Jul 2026 3 — —
Actual May 2026 — — —
5.5 Customer announcements (communicating transition timing and deadlines) Plan Aug 2026 Mar 2027 8 — —
Actual Sep 2026 — — —
5.6 Contractually repaper all customers to new data subscriber agreements Plan Sep 2026 Dec 2026 4 — —
Actual Sep 2026 — — —
5.7 Customer onboarding to new systems Plan Nov 2026 Mar 2027 5 — —
Actual — — — —
5.8 Set up financial workflow for the Plan - financial statements to the Plan - coordinate with Processors on revenue allocation - manage Plan expenses and payments - support Plan audit requirements including SOX, tax, annual, statutory Plan Jul 2026 Oct 2026 4 — —
Actual Jun 2026 — — —
5.9 Set up support for Plan governance (e.g., online board books, voting portal, document repository, drafting and tracking compliance with Confidentiality Policy and Conflicts Policy) Plan Jul 2026 Dec 2026 6 — —
Actual Jul 2026 — — —

Retirement of current plans - orderly transition

(Dependent on fees being approved, policies finalized, and Administrator fully ready to support all functions)

# Task Planned or actual Start End Months Completed % Done
6.1 CTA/UTP Plans file to cease operations (dependent on SEC approval of CT Plan fee filing) Plan Sep 2026 Oct 2026 2 — —
Actual — — — —
6.2 New Administrator begins Operations Plan Apr 2027 Apr 2027 1 — —
Actual — — — —
6.3 Assess whether current administrators need to continue after end of CTA/UTP operations to finish bill collection etc, or if those services transfer to new administrator Plan Sep 2026 Sep 2026 1 — —
Actual — — — —

CT Plan Progress Tracker · Updated quarterly through launch.